 Industry Canada Guidelines  for non-compliance by the proponent,
·      Bell Mobility:
·      Section 4.1
·      Section 4.2-2
·      Section 4.2 (Public Notification) – 2
·      Section 4.2 (Responding to the Public) – 1, 2, 3

4. Land-use Authority and Public Consultation

Contacting the Land-use Authority
Proponents must always contact the applicable land-use authorities to determine the local consultation requirements unless their proposal falls within the exclusion criteria outlined in Section 6. If the land-use authority has designated an official to deal with antenna systems, then proponents are to engage the authority through that person. If not, proponents must submit their plans directly to the council, elected local official or executive. Proponents are expected to establish initial formal contact with the land-use authority in writing in order to mark the official commencement of the 120-day consultation process.
Proponents should note that there may be more than one land-use authority with an interest in the proposal. Where no established agreement exists between such land-use authorities, proponents must, as a minimum, contact the land-use authority(ies) and/or neighbouring land-use authorities located within a radius of three times the tower height, measured from the tower base or the outside perimeter of the supporting structure, whichever is greater. As well, in cases where proponents are aware that a potential Aboriginal or treaty right or land claim may be affected by the proposed installation, they must contact Industry Canada in order to ensure that the requirements for consultation are met.
Following the Land-use Authority Process
Proponents must follow the land-use consultation process for the siting of antenna systems, established by the land-use authority, where one exists. In the event that a land-use authority's existing process has no public consultation requirement, proponents must then fulfill the public consultation requirements contained in Industry Canada's Default Public Consultation Process (see Section 4.2). Proponents are not required to follow this requirement if the LUA's established process explicitly excludes their type of proposal from consultation or it is excluded by Industry Canada's criteria. Where proponents believe the local consultation requirements are unreasonable, they may contact the local Industry Canada office in writing for guidance.
Broadcasting Undertakings
Applicants for broadcasting undertakings are subject to Canadian Radio-television and Telecommunications (CRTC) licensing processes in addition to Industry Canada requirements. Although Industry Canada encourages applicants to consult as early as practical in the application process, in some cases it may not be prudent for the applicants to initiate public and municipal/land-use consultation before receiving CRTC approval, as application denial by the CRTC would result in unnecessary work for all parties involved. Therefore, assuming that the proposal is not otherwise excluded, broadcasting applicants may opt to commence land-use consultation after having receivedCRTC approval. However, broadcasting applicants choosing this option are required, at the time of theCRTC application, to notify the land-use authority with a Letter of Intent outlining a commitment to conduct consultation after receiving CRTC approval. If the land-use authority raises concerns with the proposal as described in the Letter of Intent, applicants are encouraged to engage in discussions with the land-use authority regarding their concerns and attempt to resolve any issues. See Broadcasting Procedures and Rules, Part 1 (BPR-1), for further details.

4.1 Land-use Authority Consultation

Industry Canada believes that any concerns or suggestions expressed by land-use authorities are important elements to be considered by proponents regarding proposals to install, or make changes to, antenna systems. As part of their community planning processes, land-use authorities should facilitate the implementation of local radiocommunication services by establishing consultation processes for the siting of antenna systems.
Unless the proposal meets the exclusion criteria outlined in Section 6, proponents must consult with the local land-use authority(ies) on any proposed antenna system prior to any construction with the aim of: 
  • discussing site options;
  • ensuring that local processes related to antenna systems are respected;
  • addressing reasonable and relevant concerns (see Section 4.2) from both the land-use authority and the community they represent; and
  • obtaining land-use authority concurrence in writing.
Land-use authorities are encouraged to establish reasonable, relevant, and predictable consultation processesFootnote2 specific to antenna systems that consider such things as:
  • the designation of suitable contacts or responsible officials;
  • proposal submission requirements;
  • public consultation;
  • documentation of the concurrence process; and
  • the establishment of milestones to ensure consultation process completion within 120 days.
Where they have specific concerns regarding a proposed antenna system, land-use authorities are expected to discuss reasonable alternatives and/or mitigation measures with proponents.
Under their processes, land-use authorities may exclude from consultation any antenna system installation in addition to those identified by Industry Canada's own consultation exclusion criteria (Section 6). For example, an authority may wish to exclude from public consultation those installations located within industrial areas removed from residential areas, low visual impact installations, or certain types of structures located within residential areas.

4.2 Industry Canada's Default Public Consultation Process

Proponents must follow Industry Canada's Default Public Consultation Process where the local land-use authority does not have an established and documented public consultation process applicable to antenna siting. Proponents are not required to follow Industry Canada's Default Public Consultation Process if the land-use authority's established process explicitly excludes their type of proposal from public consultation or it is excluded by Industry Canada's criteria (see Section 6). Industry Canada's default process has three steps whereby the proponent: 
  1. provides written notification to the public, the land-use authority and Industry Canada of the proposed antenna system installation or modification (i.e. public notification);
  2. engages the public and the land-use authority in order to address relevant questions, comments and concerns regarding the proposal (i.e. responding to the public); and
  3. provides an opportunity to the public and the land-use authority to formally respond in writing to the proponent regarding measures taken to address reasonable and relevant concerns (i.e.public reply comment).
Public Notification
  1. Proponents must ensure that the local public, the land-use authority and Industry Canada are notified of the proposed antenna system. As a minimum, proponents must provide a notification package (see Appendix 2) to the local public (including nearby residences, community gathering areas, public institutions, schools, etc.), neighbouring land-use authorities, businesses, and property owners, etc. located within a radius of three times the tower height, measured from the tower base or the outside perimeter of the supporting structure, whichever is greater. For the purpose of this requirement, the outside perimeter begins at the furthest point of the supporting mechanism, be it the outermost guy line, building edge, face of the self-supporting tower, etc.
  2. It is the proponent's responsibility to ensure that the notification provides at least 30 days for written public comment.
  3. In addition to the minimum notification distance noted above, in areas of seasonal residence, the proponent, in consultation with the land-use authority, is responsible for determining the best manner to notify such residents to ensure their engagement.
  4. In addition to the public notification requirements noted above, proponents of antenna-supporting structures that are proposed to be 30 metres or more in height must place a notice in a local community newspaper circulating in the proposed area.Footnote3
Responding to the Public
Proponents are to address all reasonable and relevant concerns, make all reasonable efforts to resolve them in a mutually acceptable manner and must keep a record of all associated communications. If the local public or land-use authority raises a question, comment or concern relating to the antenna system as a result of the public notification process, then the proponent is required to: 
  1. respond to the party in writing within 14 days acknowledging receipt of the question, comment or concern and keep a record of the communication;
  2. address in writing all reasonable and relevant concerns within 60 days of receipt or explain why the question, comment or concern is not, in the view of the proponent, reasonable or relevant; and
  3. in the written communication referred to in the preceding point, clearly indicate that the party has 21 days from the date of the correspondence to reply to the proponent's response. The proponent must provide a copy of all public reply comments to the local Industry Canada office.
Responding to reasonable and relevant concerns may include contacting a party by telephone, engaging in a community meeting or having an informal, personal discussion. Between steps 1 and 2 above, the proponent is expected to engage the public in a manner it deems most appropriate. Therefore, the letter at step 2 above may be a record of how the proponent and the other party addressed the concern at hand.
Public Reply Comments
As indicated in step 3 above, the proponent must clearly indicate that the party has 21 days from the date of the correspondence to reply to the response. The proponent must also keep a record of all correspondence/discussions that occurred within the 21-day public reply comment period. This includes records of any agreements that may have been reached and/or any concerns that remain outstanding.
The factors that will determine whether a concern is reasonable or relevant according to this process will vary but will generally be considered if they relate to the requirements of this document and to the particular amenities or important characteristics of the area surrounding the proposed antenna system. Examples of concerns that proponents are to address may include: 
  • Why is the use of an existing antenna system or structure not possible?
  • Why is an alternate site not possible?
  • What is the proponent doing to ensure that the antenna system is not accessible to the general public?
  • How is the proponent trying to integrate the antenna into the local surroundings?
  • What options are available to satisfy aeronautical obstruction marking requirements at this site?
  • What are the steps the proponent took to ensure compliance with the general requirements of this document including the Canadian Environmental Assessment Act (CEAA), Safety Code 6, etc.?



No comments: